December 14, 2006
Controlling Project Costs
Controlling Cost in a project is the only way to assure the within budget part of a successful project. Cost control involves being diligent of about requested changes and handling those changes through the integrated change control process. A change request can vary between a potential overrun of authorized funding to inappropriate resource usage.
As with all things PMI, there are inputs, tools and techniques, and outputs of cost control.
The inputs are:
- Performance reports – Performance reports provide the actual costs and resource usage based upon completed work. Performance reports yield information on work progress, some common formats are the bar chart, S-curves, histograms, table, and network diagrams which illustrate the current schedule status.
- Approved change requests – An approved change request is one that has been successfully through the Integrated Change Control process and given the stamp of approval.
- Cost Baseline – The cost baseline is a time-phased budget. The purpose of the cost baseline is to provide a basis against which to measure, monitor, and control the overall project’s cost performance.
- Project funding requirements – Project funding requirements are based upon the cost baseline and contingency reserves. Let’s say that a task is running late and there is a change request to add another resource. A PM may look at the baseline and contingency reserves to determine the money is available.
- Project Management Plan - The Project Management Plan and its subsidiary cost management plan details the organizational policies and procedures which need to be followed.
- Work performance information – Work performance information contains the current status on deliverables, costs, and the schedule.
There are common tools and techniques which PMs use to control costs. They are:
- Cost change control system – The cost change control system is a component of integrated change control. Defined in the cost management plan, the change control system lists how cost changes are handled and what is needed to handle these changes.
- Performance measurement analysis – Performance measurement analysis is the usage of the earned value techniques to identify variances and determine if corrective action is needed.
- Forecasting – Forecast is how estimates or prediction of the project’s future are made. This process includes the calculation of EAC, BAC, and ETC.
- Project performance reviews – Project performance reviews compare the activity costs over time, scheduled activities, and milestone progress.
- Project management software – PMIS can be utilized to track costs and forecast the effect of changes on estimated costs. This information can be used to support suggested changes.
- Variance management – Variance management illustrates the varying degrees of variances should be managed. The various management techniques to use on a project are commonly found in the Cost Management Plan. Ideally there is a different way of handling small variances to large variances.
So after engaging in the cost control process, what are the end results? The outputs of controlling cost are:
- Cost estimate updates – Cost estimate updates are approved changes that result in an update to the project documents which depict cost information – normally the activity cost estimate document.
- Recommended corrective actions – Recommended corrective actions are steps which should be by the project management team to ensure that any future work supports the current Project Management Plan.
- Forecasted completion – Forecasted completion is the calculated estimate at completion or the estimate to completion. This value is communicated to the stakeholders and sponsors.
- Requested changes – Request changes are normally resulting from the recommended corrective actions.
- Organizational process assets updates – Organizational process updates are the enhancement added to the organizational process documents. For example, lessons learned on why a schedule variance occurred and how it was resolved.
- Performance measurements – Performance measurement are the calculated earned values used to monitor project cost performance. Typically the CV, CPI. SV, and SPI.
- Cost baseline updates – Cost baseline updates are approved changes to the current cost baseline. By updating the baseline one can use it as a realistic measure against which project cost performance can be judged.
- Project Management Plan updates – Project Management Plan updates encompass any approved changes to the project management plan or any subsidiary management plans.
A key point is that one measure a pm can take to assure a successful project is to control the costs of that project.
Posted by Elyse at December 14, 2006 11:28 AM
Comments
Post a comment
Did you miss?
IT Governance, the decisions needs by whom
Finally passed the test
Managing in light of McGregor's Theory X and Theory Y
CMMI
Kicking HIT Leadership Up a Notch
That's just some mumbo jumbo project management BS
Outcomes - The tactic to get to the strategy
Nurse Call, VOIP, and Wi-Fi: Its just cool when things come together!
Finally passed the test
Managing in light of McGregor's Theory X and Theory Y
CMMI
Kicking HIT Leadership Up a Notch
That's just some mumbo jumbo project management BS
Outcomes - The tactic to get to the strategy
Nurse Call, VOIP, and Wi-Fi: Its just cool when things come together!
Archives
January 2008
December 2007
November 2007
October 2007
September 2007
August 2007
July 2007
June 2007
May 2007
April 2007
March 2007
February 2007
January 2007
December 2006
November 2006
August 2006
June 2006
May 2006
April 2006
March 2006
February 2006
January 2006
November 2005
October 2005
September 2005
August 2005
June 2005
May 2005
April 2005
March 2005
February 2005
January 2005
December 2004
November 2004
October 2004
September 2004
August 2004
July 2004
June 2004
May 2004
April 2004
March 2004
February 2004
January 2004
December 2003
November 2003
October 2003
December 2007
November 2007
October 2007
September 2007
August 2007
July 2007
June 2007
May 2007
April 2007
March 2007
February 2007
January 2007
December 2006
November 2006
August 2006
June 2006
May 2006
April 2006
March 2006
February 2006
January 2006
November 2005
October 2005
September 2005
August 2005
June 2005
May 2005
April 2005
March 2005
February 2005
January 2005
December 2004
November 2004
October 2004
September 2004
August 2004
July 2004
June 2004
May 2004
April 2004
March 2004
February 2004
January 2004
December 2003
November 2003
October 2003
Blogs
Cafe au Lait
Joel on Software
David Ross
Edward Prevost
Martin Fowler
The Health Care Blog
The Tales of Hoffman
The Business Word
Medical Rants
Christina's Considerations
Paul Levy
HIS Talk
Appropriate IT
Candid CIO
Joel on Software
David Ross
Edward Prevost
Martin Fowler
The Health Care Blog
The Tales of Hoffman
The Business Word
Medical Rants
Christina's Considerations
Paul Levy
HIS Talk
Appropriate IT
Candid CIO
Subscribe
© Copyright 2003 - 2007 Elyse Nielsen
RSS feed




