December 8, 2006
PMI Earned Value Management Terms and Formulas
Earned Value Management is a way to measure a project’s performance against the project baseline. An earned value analysis can clue the project manager into trending deviations from the project’s cost and schedule plans. Earned Value Management integrates cost, time, and scope completed. It is very useful in forecasting future performance.
The Terminology
| Acronym | Term | Description |
|---|---|---|
| PV | Planned Value | PV is the authorized budget assigned to the scheduled work to be accomplished for a scheduled activity or work breakdown structure component. |
| EV | Earned Value | EV is the value of completed work expressed in terms of the approved budget assigned to that work for a scheduled activity or work breakdown structure component. The cumulative EV is the sum of the approved budgets for activities completed during a given period. |
| AC | Actual Cost | AC is the total costs incurred and recorded in accomplishing work performed during a given time period for a scheduled activity or work breakdown structure component. Actual cost can sometimes be direct labor hours alone; direct costs alone; or all costs, including indirect costs |
| BAC | Budget at Completion | BAC is the total amount of funds to be spent at the completion of the task. |
| EAC | Estimate at Completion | EAC is used by project managers to give their best estimate of the total costs of projects based on actual costs to date. The most frequently used formula for EAC is AC plus ETC; this formula is typically used when previous assumptions regarding costs are wrong. |
| ETC | Estimate to Complete | ETC is the expected cost needed to complete all the remaining work for a scheduled activity, a group of activities, or the project. ETC helps project managers predict what the final cost of the project will be upon completion. |
| VAC | Variance at Completion | VAC forecasts the difference between the Budget-at-Completion and the expected total costs to be accrued over the life of the project based on current trends. |
The Formulas
| Acronym | Term | Formula | Description |
|---|---|---|---|
| CV | Cost Variance | CV = EV - AC | CV provides the cost performance of the project to help determine whether the project is proceeding as planned. Subtracting AC from EV calculates the cost variance. |
| SV | Schedule Variance | SV = EV - PV | SV indicates the project's schedule performance. This value can indicate whether the project work is proceeding as planned. Calculate the SV by subtracting the PV from the EV. |
| CPI | Cost Performance Index | CPI = EV / AC | For the CPI of individual budgets, divide EV by AC. For a cumulative CPI, divide the sum of all EV budgets by the sum of all ACs. A CPI of less than one indicates that the project is over budget, and a CPI of over one indicates that the project is coming in under the estimated budget. |
| SPI | Schedule Performance Index | SPI = EV / PV | Project managers can use the SPI to help predict when their projects will be completed. To calculate the SPI, divide EV by PV. An SPI of one indicates the project is on schedule; greater than one indicates it is ahead of schedule; and less than one indicates it is behind schedule. |
| EAC | Estimate at Completion | EAC = BAC / CPI EAC = AC + ETC EAC = AC + (BAC - EV) |
EAC is used by project managers to give their best estimate of the total costs of projects based on actual costs to date. The most frequently used formula for EAC is AC plus ETC; this formula is typically used when previous assumptions regarding costs are wrong. |
| ETC | Estimate to Complete | ETC = EAC - AC | ETC is the expected cost needed to complete all the remaining work for a scheduled activity, a group of activities, or the project. ETC helps project managers predict what the final cost of the project will be upon completion. |
| VAC | Variance at Completion | VAC = BAC - EAC | VAC forecasts the difference between the Budget-at-Completion and the expected total costs to be accrued over the life of the project based on current trends. |
| CPIc | Cumulative Cost Performance Index | CPIc = Σ EV / Σ AC | Cumulative CPI Method forecasts the total amount to be spent by adding costs incurred to date to the remaining work to be earned, which has been weighted against the current CPI performance value. Starts from the 20 percent completion point. |
Posted by Elyse at December 8, 2006 7:21 AM
Comments
Thanks so much for posting this. It's Thursday at 7:34pm and I'm taking the PMI CAPM Saturday morning. Needless to say I'm in a studying frenzy! Your descriptions are a great help for me in solidifying my understanding of these terms. Right on time - thanks again!
Cheers!
Melissa
Post a comment
Did you miss?
Himss - Final Thoughts
HIMSS 2008 Perceptions - A first glance
Our best intentions and the effects of not collaborating
Quick Little Risk Management Checklist
Tasks, Projects, Programs
IT Value: Is it an Expense Center or a Value Center
Planning and Managing Risk
Graphical Hospital Quality Ranking by Locale
HIMSS 2008 Perceptions - A first glance
Our best intentions and the effects of not collaborating
Quick Little Risk Management Checklist
Tasks, Projects, Programs
IT Value: Is it an Expense Center or a Value Center
Planning and Managing Risk
Graphical Hospital Quality Ranking by Locale
Archives
March 2008
February 2008
January 2008
December 2007
November 2007
October 2007
September 2007
August 2007
July 2007
June 2007
May 2007
April 2007
March 2007
February 2007
January 2007
December 2006
November 2006
August 2006
June 2006
May 2006
April 2006
March 2006
February 2006
January 2006
November 2005
October 2005
September 2005
August 2005
June 2005
May 2005
April 2005
March 2005
February 2005
January 2005
December 2004
November 2004
October 2004
September 2004
August 2004
July 2004
June 2004
May 2004
April 2004
March 2004
February 2004
January 2004
December 2003
November 2003
October 2003
February 2008
January 2008
December 2007
November 2007
October 2007
September 2007
August 2007
July 2007
June 2007
May 2007
April 2007
March 2007
February 2007
January 2007
December 2006
November 2006
August 2006
June 2006
May 2006
April 2006
March 2006
February 2006
January 2006
November 2005
October 2005
September 2005
August 2005
June 2005
May 2005
April 2005
March 2005
February 2005
January 2005
December 2004
November 2004
October 2004
September 2004
August 2004
July 2004
June 2004
May 2004
April 2004
March 2004
February 2004
January 2004
December 2003
November 2003
October 2003
Blogs
Cafe au Lait
Joel on Software
David Ross
Edward Prevost
Martin Fowler
The Health Care Blog
The Tales of Hoffman
The Business Word
Medical Rants
Christina's Considerations
Paul Levy
HIS Talk
Appropriate IT
Candid CIO
Joel on Software
David Ross
Edward Prevost
Martin Fowler
The Health Care Blog
The Tales of Hoffman
The Business Word
Medical Rants
Christina's Considerations
Paul Levy
HIS Talk
Appropriate IT
Candid CIO
Subscribe
© Copyright 2003 - 2007 Elyse Nielsen
RSS feed




