The WBS is:
- A deliverables-oriented collection of project components
- Serves as the project scope baseline.
The WBS is an input to:
- Cost Estimating
- Cost Budgeting
- Resource Planning
- Risk Management
- Activity Definition
The WBS Dictionary explains the WBS components, assigned resources, time and cost for each element.
The WBS 8/80 Rule is that Activiteis from the WBS should not take more than 80 hours or less than eight hours.