January 20, 2005
Earned Value Components
Earned Value Management (EVN) is a management technique that relates resource planning to schedules and costs in time-phased increments. It allows for accurate assessments of status to date and is utilized to calculate estimates to completion of project.
Earned value refers to a cost-based performance measurement that compares the amount of work that was planned with what was actually performed to determine if cost and schedule are proceeding as planned. Earned value analysis provides a more accurate view than looking at cost or schedule variance separately. This information alerts the corrective action that must be taken to complete the project successfully.
The elements of earned value:
- Budgeted Cost of Work Scheduled (BCWS) The estimate of costs needed to complete the scheduled project work.
- Budgeted Cost of Work Performed (BCWP) The estimated of costs for work actually completed. Also know as Earned Value.
- Actual Cost of Work Performed (ACWP) The cost of completing the project work
To calculate earned value:
- Calculate the Budgeted Cost of Work Scheduled (BCWS) for a given period. These amounts were determined when you develop the project budget and should be available from the baseline in MS Project.
- Estimate the percent complete of the work scheduled for the given time period.
- Calculate the Budged Cost of Work Performed (BCWP), or earned value, for the same time period by taking the percent complete of work times the BCWS.
- Calculate Actual Cost of Work Performed (ACWP) for the same period by determining the actual amount of money that has been spent on the work for this time period
In project to see this by a cost per task. Select the Gantt Tracking, then View -> Table -> cost
Finally passed the test
Managing in light of McGregor's Theory X and Theory Y
CMMI
Kicking HIT Leadership Up a Notch
That's just some mumbo jumbo project management BS
Outcomes - The tactic to get to the strategy
Nurse Call, VOIP, and Wi-Fi: Its just cool when things come together!
December 2007
November 2007
October 2007
September 2007
August 2007
July 2007
June 2007
May 2007
April 2007
March 2007
February 2007
January 2007
December 2006
November 2006
August 2006
June 2006
May 2006
April 2006
March 2006
February 2006
January 2006
November 2005
October 2005
September 2005
August 2005
June 2005
May 2005
April 2005
March 2005
February 2005
January 2005
December 2004
November 2004
October 2004
September 2004
August 2004
July 2004
June 2004
May 2004
April 2004
March 2004
February 2004
January 2004
December 2003
November 2003
October 2003
Joel on Software
David Ross
Edward Prevost
Martin Fowler
The Health Care Blog
The Tales of Hoffman
The Business Word
Medical Rants
Christina's Considerations
Paul Levy
HIS Talk
Appropriate IT
Candid CIO
RSS feed




